Date |
Activity |
|
July 1st |
Start of financial year |
|
July 10 |
Receipt of Annual Review Progress Reports from Line Departments along with details of lapses/excess of funds |
|
July end |
Sectoral annual review of ADP |
|
August start |
Joint Annual Review of ADP of previous year with Chief Minister/Governor |
|
September mid |
Circulation of proformae for 1st quarter review of ADP progress |
|
October mid |
Sectoral review 1st quarter |
|
November start |
Joint review |
|
November End |
Call letters to Line Department for Next year ADP schemes |
|
December start |
Submission of schemes to Finance Department for transfer to recurrent budget |
|
December end |
Submission of foreign aid revised estimates |
|
January start |
Approval of unapproved new schemes |
|
January mid |
Progress reports for mid-year review of ADP |
|
January mid |
Receipt of proposals for next year ADP from departments |
|
January end |
Tentative sectoral sizes of ADP endorsed to departments |
|
-do- |
Mid-year sectoral review |
|
February start |
Joint mid-year review |
|
February mid |
Priorities Committee Meetings |
|
March |
Finalisation of ADP |
|
Submission to Federal Government |
|
Revision of schemes from PDWP |
|
April |
Incorporation of schemes/modifications in ADP |
|
3rd quarter review |
|
Re-appropriations |
|
May |
Revised estimates for Finance Department for incorporation in Budget |
|
Final ADP draft |
|
APCC meeting in Federal Government |
|
Approval of ADP |
|
June |
NEC meeting |
|
Final ADP |